Under Zero-Based Budgeting (ZBB), which statement is correct?

  • A Every programme must justify its entire budget afresh each cycle, starting from zero
  • B Each year's budget starts from the previous year's allocation plus an increment
  • C Only new programmes are funded while ongoing programmes continue automatically
  • D The budget is fixed at zero growth regardless of inflation
Correct answer: A. Every programme must justify its entire budget afresh each cycle, starting from zero

Explanation

In zero-based budgeting every activity and programme must be justified completely in each budgeting cycle, beginning from a base of zero, without assuming that last year's funding continues. Option B describes incremental or traditional budgeting, which ZBB was designed to replace. Option C is the opposite of ZBB because ongoing activities receive no automatic continuation, and option D misreads the term zero as referring to growth rate rather than the starting base of justification.

Reference: Park's Textbook of Preventive and Social Medicine, 27th ed.

High-yield for: NEET PGINI-CETNExTFMGEUSMLEPLABMRCP

Written and medically reviewed by the StethoPrep medical team.

Sponsored

Want to test yourself?

Create a free account for timed mock tests, mistake tracking, and FSRS spaced-repetition revision across 43,000+ MCQs.

Start free → Log in

More Health Planning, Management and International Health MCQs

See all Health Planning, Management and International Health MCQs →