Community Medicine (PSM) · Health Planning, Management and International Health

A programme manager uses PERT network analysis to schedule the construction of a rural health centre. In such a network diagram, the 'critical path' is defined as:

  • A The shortest sequence of activities through the network
  • B The path with the largest number of activities
  • C The path containing all activities with the lowest cost
  • D The longest path through the network, which determines minimum project duration
Correct answer: D. The longest path through the network, which determines minimum project duration

Explanation

The critical path is the longest time-consuming chain of dependent activities from start to finish; it fixes the minimum time in which the whole project can be completed, and any delay along it delays the entire project. It is not the cheapest path nor the one with most activities. Activities off the critical path have slack time and can absorb some delay without affecting completion date.

Reference: Park's Textbook of Preventive and Social Medicine, 27th ed.

High-yield for: NEET PGINI-CETNExTFMGEUSMLEPLABMRCP

Written and medically reviewed by the StethoPrep medical team.

Sponsored

Want to test yourself?

Create a free account for timed mock tests, mistake tracking, and FSRS spaced-repetition revision across 43,000+ MCQs.

Start free → Log in

More Health Planning, Management and International Health MCQs

See all Health Planning, Management and International Health MCQs →